Advance to content | List of Access Keys |

Appendix A: Questions

Question 1

Council receives a complaint of a spray-drift incident. Staff inspect immediately and collect evidence to establish:

The concentration of pesticide applied exceeds the manufacturer’s instructions and there are significant adverse effects of off-target drift. Plants on neighbouring properties have been damaged. Sea Helicopters informs Council that s 20A applies, that it has been spraying pesticides for 20 years, and that Council cannot take enforcement action because Sea Helicopters is not required to comply with the proposed plan until the plan is operative. What can Council do?

Answer

Council can apply for an interim enforcement order or an enforcement order, or issue an abatement notice requiring Sea Helicopters to comply with the s 17 duty.

back to top

Question 2

In the above scenario, Sea Helicopters sprays pesticide for five months each year. Can Council argue that s 20A does not apply because the activity has been discontinued for a continuous period of more than six months?

Answer

No. The Environment Court has noted that care is required in applying the six-month discontinuity test to seasonal activities like fruit picking, because an absence of activity at a time of year when none would normally be carried on anyway would not be evidence of the use having been discontinued (Wairoa Coolstores (1994) Ltd v Western Bay of Plenty District Council [1998]).

back to top

Question 3

The Transitional Regional Plan general authorisation 3 allows up to 15 cubic metres of water per day to be taken for reasonable domestic needs and the needs of animals. The proposed plan rule 3.3.4.8 allows 30 cubic metres per day of ground water to be taken. Joe Bloggs takes 30 cubic metres of water per day. Mr Bloggs’s neighbour complains that Bloggs is not complying with the general authorisation number 3. Is Mr Bloggs required to comply with general authorisation 3?

Answer

Mr Bloggs is required to comply with the Transitional Regional Plan and the Proposed Plan. The Transitional Regional Plan is the more restrictive, and therefore Mr Bloggs can only take up to 15 cubic metres of water per day.

back to top

Question 4

Assume that the Transitional Regional Plan general authorisation number 14a provides that the discharge of clean stormwater to the ground is permitted subject to certain conditions. Assume that under the Proposed Plan, discharge of stormwater onto or into land from a quarry is a controlled activity. Is a quarry that was operating before notification of the Proposed Plan allowed to continue to discharge stormwater to land without a resource consent?

Answer

Section 20A applies if the quarry meets the conditions in s 20A(1)(a), (b) and (c), and the quarry can continue to discharge stormwater to land without a resource consent.

back to top