Auckland Regional Council structure planning process

Return to point in document this figure is located

Text description of figure

The flowchart shows the structure planning process followed by Auckland Regional Council.

The first step is to define the plan structure area by considering:

  • Quantum and form/intensity of growth - indicated by RGA and sector planning
  • Context relative to catchment boundaries
  • Natural resource values and infrastructure capabilities

The next step is to identify the stakeholders by considering

  • People who live or work in the area
  • People whose property interests are affected
  • Community interests
  • Iwi
  • Infrastructure provisers/operators
  • Service providers

The next step is to assemble natural resource and heritage information by considering

  • Natural resource context
    • Catchment boundaries and characteristics
    • Resolving waters' quality/sensitivity
    • Landform's slope, vegetation, erodability
  • Heritage information
    • Places/features valued by Māori
    • Places/features from early pakeha days
    • Landscape values

Then the task is to assemble physical resource information by considering:

  • Access
    • Road network links' capacities
    • Public transport services
  • Infrastructure capacity thresholds
    • Sanitary sewerage
    • Stormwater
    • Water supply
    • Energy communications

From there a map must be drawn of the process. Consultation to agree on ground rules is performed (background information is provided to stakeholders that includes a process map and proposed ground rules). Input to the consultation is received regarding:

  • Development objectives
  • Constraints' opportunities
  • Resource values
  • Stakeholders' ideas/preferences

From the feedback, development options are generated and evaluted. This is presented back to stakeholders and:

  • Matters agreed on
  • Development options
  • Evaluate options.

If required, further consultation is conducted to:

  • Obtain further comment
  • Fine-tune preferred option
  • Decide programme and funding

The structure plan is then implemented. The territorial authority changes or varies the district plan
Territorial authorities and infrastructure/service providers provision:

  • LTFSs
  • Annual plans
  • Asset management plans

Finally, Regional Growth Forum and Territorial Authorities monitor implementation, restarting the process as required.