Managing Earthworks under the Resource Management Act

Abstract

Earthworks can generate a variety of adverse effects on land, air and water bodies, with the significance of these effects varying depending on their scale and the environment within which they occur.

Regional councils and territorial authorities are jointly responsible for managing the effects of earthworks under the Resource Management Act (RMA) and this arrangement can result in jurisdictional confusion.

To help practitioners understand the effects of earthworks and to better equip them to address the challenge of managing these effects, this guidance note aims to:

Guidance Note

Introduction

Earthworks: Issues and Effects

Functions of Regional and District Councils in Managing Effects of Earthworks

Definition of ‘Earthworks’ in Regional and District Plans

Methods for Managing the Effects of Earthworks in RMA Plans

Regulatory methods

Introduction

Managing earthworks is a complex issue. This is due in part to the wide range of activities covered by the term ‘earthworks’, as well as the wide range of effects generated. It is also further complicated by:

back to top

Earthworks: Issues and Effects

Earthworks involve revealing, disturbing or depositing soil which results in the creation of exposed surfaces.  These surfaces are created by activities such as land contouring for urban development and roading, quarrying, filling operations (including cleanfills), clearing vegetation, forestry, agriculture and horticulture.

If not managed well, earthworks have the potential to cause significant adverse effects on the environment such as:

back to top

Functions of Regional and District Councils in Managing Effects of Earthworks

Resource Management Act 1991

Regional council responsibilities

Section 30 of the RMA sets out the statutory responsibilities of regional councils. These include controlling the use of land for soil conservation purposes, maintenance and enhancement of water quality and ecosystems, and controlling discharges of contaminants.

Definition of Contaminant

Under Section 2 of the RMA “contaminant” is defined as

“includes any substance (including gases [odourous compounds,] liquids, solids, and micro-organisms) or energy (excluding noise) or heat, that either by itself or in combination with the same, similar or other substances, energy or heat –
(a) When discharged into water, changes or it likely to change the physical, chemical, or biological condition of water; […]”

[ Hide ]

 

Accelerated loads of sediment have the ability to change the physical, chemical, or biological condition of water and therefore fall within the definition of ‘contaminant’ under the RMA.

Two primary approaches available to regional councils to manage the effects of earthworks are:

Territorial local authority responsibilities

Section 31(1) of the RMA sets out the statutory responsibilities for territorial local authorities.  Controlling the use, development or subdivision of land covers a wide range of issues, including vegetation cover, amenity values, infrastructure, roading, and natural hazards. As earthworks can have adverse effects on all these matters, territorial local authorities will need to evaluate how these matters are to be appropriately managed.

Managing potential overlap between regional and city/district councils

Regional and city/district councils are responsible for controlling different aspects of earthwork activities. Consequently, councils need to direct specific attention towards the mechanisms they use to manage areas of potential overlap and to ensure that unnecessary duplication of consent processes is avoided.

Typically regional councils focus on the effects of earthworks on water quality and ecosystems, and city/district councils tend to focus on land-use effects such as amenity. However, blurring of these functions does occur and can result in duplication, particularly in relation to consents.

Auckland Regional Council Water Quality Research

Until recently the effects of land generated sediment on the habitat values of waterbodies was not well understood. Over the last 10 years a considerable amount of research has been undertaken in the Auckland region on the effects of accelerated loads of sediment entering water bodies (refer “ARC Technical Publication 264 – Effects of sedimentation on macrofaunal communities: a synthesis of research studies for ARC).

However, it is important to recognise that Auckland soils, particularly clay soils, have particular characteristics, including the ability to remain in suspension for extended periods of time. This is due to their very fine texture and their ability to be readily conveyed to lower receiving environments vulnerable to elevated sediment loading and sediment deposition.  Consequently, this research may not be readily applicable in all parts of New Zealand as the effects of sediment discharge on water quality will depend on the type of soil and land use of the contributing catchment, together with the characteristics of the receiving environment.

[ Hide ]

 

To address this situation more effective reliance on regional policy statements could be made by regional councils to help clarify respective functional responsibilities. In particular, policies and methods should be included that clearly identify how the effects of earthworks activities are to be managed across the region and by whom. This is particularly relevant now that district plans are required to give effect to regional policy statements under s75(3) of the RMA.

Particular steps that local authority practitioners should consider concerning overlapping functional responsibilities include:

back to top

Definition of ‘Earthworks’ in Regional and District Plans

The term ‘earthworks’ is used in a wide range of situations.  It is not exclusively referred to in plans as other related terms such as ‘soil disturbance’, ‘land modification’ and ‘excavations’ are also commonly used.

As a variety of definitions apply to these terms a range of differing interpretations of ‘earthworks’ can result. Some definitions also include a range of exclusions, such as cleanfilling, quarrying, normal household gardening practices, and horticultural and pastoral farming activities.

The Environment Court has been asked to determine the meaning of ‘earthworks’ on a number of occasions (refer Case Law). Based on these determinations, a definition of earthworks should include details on what physical activities constitute earthworks, such as:

Any list which forms part of a definition should describe the common physical works and methods of earthwork activities. The definition should not include minimum/maximum thresholds (eg, excavations in excess of 1.0m in depth), as these should form part of the associated rules (performance standards and terms). Two best practice examples of a working definition for earthworks are:

back to top

Methods for Managing the Effects of Earthworks in RMA Plans

Research and background investigations

The following should be used as a guide when preparing plan provisions to manage earthworks:

Consultation: Consultation should be based on commissioned technical reports and focus on parties directly associated with earthwork activities, such as contractors, engineers, forestry companies and developers (refer Consultation Guidance Note for more information on consultation).

Definitions: To avoid confusion and misunderstanding include clear definitions of terms in plans (See Definitions section above).

Technical expertise

It is important to obtain technical/engineering advice to determine both the effects of earthwork activities and appropriate methods to manage their effects.

Rules and methods to manage the effects of earthworks for resource consent or policy/plan purposes should consider issues such as soil type, soil characteristics, topography and sensitivity of the receiving waters to any sediment runoff. Technical expertise should be used to assist in understanding different interactions and natural processes.

Experts with an understanding of earthwork processes, operations and environmental impacts will help in identifying methods to manage the effects of earthworks which are effective, efficient and workable.

Translating the science around earthworks effects into specific policy guidance can be challenging and development of a process to reconcile conflicting advice should be considered.

Evaluation and assessment

An assessment of the region/district and the risks posed by earthworks is a first step in any evaluation. The costs and benefits of the methods selected to manage earthwork activities will also need to be carefully considered (refer to the Examples of Costs and Benefits for Earthworks and the Section 32 Guidance Note).

A number of the effects from earthworks are interrelated. Methods should be evaluated and adapted to reflect the local environmental conditions (ie, soil characteristics, topography, climate, and sensitivity of receiving waters to sediment runoff). Successful methods used in other regions/districts should be evaluated based on local environmental conditions before being applied in other areas.

Avoiding earthworks: it may be appropriate to avoid subdivision and development in certain locations due to the sensitivity of the receiving environment (refer to Okura Catchment in North Shore City, Relevant Case Law).

Objectives and policies in regional/district plans

(Also refer Plan Framework Guidance Note)

back to top

Regulatory methods

Rules in regional/district plans

(Also refer Writing provisions for regional and district plans)

Rules are the primary method used by councils to manage the effects of earthworks. Regional councils generally have a “Sediment Control” or “Land Disturbance” regional plan to regulate earthworks and sediment discharges (refer ARC Best Practice Example).  The ARC Sediment Control Plan is an example of such an approach and adopts an effects-based approach to sediment control, including rules relating to sensitive environments (ie, riparian areas), soil types and topography.  Rules can be developed where they apply to a whole region/city/district or on a catchment basis, and can establish varying activity status and thresholds.

Region/city/district wide versus catchment wide

There are two broad regulatory approaches used to manage earthworks:

In some situations, both approaches might be used – general rules applying to the region/city/district with targeted provisions applying to more sensitive areas.

Activity status and thresholds

Activity status and associated thresholds are a common method used by regional and territorial authorities to manage earthworks. Thresholds can be based on such factors as the area, volume, height/depth of a cut/fill or slope of an earthwork (refer Regional and District Plan Best Practice Examples).

Resource consent applications

Resource consent applications should include erosion and sediment control plans when associated earthworks are likely to cause significant adverse effects. This will ensure there is sufficient information available to assess the effects of the proposal, and the ability to avoid, remedy or mitigate these effects.

Resource consent conditions

Resource consent conditions are the primary means by which the effects of earthwork activities are controlled and managed.  Conditions can cover:

Refer to Conditions of Resource Consents for examples of generic conditions.

In imposing conditions on resource consents, it is important to recognise that no sediment control techniques are 100 percent effective. These techniques minimise, but do not avoid, the sediment load discharged to the receiving environment (refer to an example of sediment catchment yield under different sediment control scenarios relating to the northern motorway extension of State Highway 1 (ALPURT B2)).

To ensure compliance a combination of active monitoring of consent conditions and consent holder self-monitoring is required. In addition, integrated monitoring between regional and territorial local authorities can assist in managing the effects of earthworks.

Bylaws

Under ss. 145 and 146 of the LGA 2002, territorial local authorities can make bylaws for the purposes of protecting the public from nuisance, for public health and safety and to protect infrastructure. Consequently, bylaws can be prepared to control and manage the effects of earthworks and the discharge of sediment for these purposes.

Codes of practice/standards

Codes of practice/standards have been developed at both national and local levels. Some codes are directly referenced in plans, while others are administered outside of RMA processes (refer Guidance Note on Writing provisions for regional and district plans). Prior to adopting any nationally based standards, local authorities should assess their suitability relative to their own individual circumstances.

Non-regulatory methods

Guidelines/ practice notes
Education
Integrated management techniques

Other legislative requirements

Other legislation also indirectly manages activities associated with earthworks.

back to top

Best Practice Examples

Regional plans

Two approaches are available to manage the effects of earthworks in regional plans: controlling land-use activity and controlling discharge of sediment. Some regional councils use a combination of both these approaches. The choice of approach will depend on regional characteristics.

Controlling Land-use activities of earthworks

This approach relies on s.9 of the RMA to control earthwork activities.  Where land-use activities are regulated by a plan, the discharge of associated sediment can be permitted under s.15 of the RMA provided the land-use activity is either permitted or granted  consent under s.9 of the RMA.

Regional councils that have adopted this approach include:

Controlling discharge of sediment from earthworks

This approach relies on s.15 of the RMA to control the discharge of sediment from earthwork activities by developing policies and methods based on water quality standards.  In determining standards for permitted activities, regard is had to the provisions in s.70 of the RMA.

Regional councils that have adopted this approach include:

Permitted activities

The range of permitted activity thresholds specified in regional plans is quite broad and can cover:

Further controls may be used in circumstances where earthworks have the potential to cause significant adverse effects.

Additional Regional Plan Regulatory Methods

  • Restrictions on the time of year/ season, in which earthwork activities can occur;
  • Limits on concentrations of sediment in site runoff;
  • Avoidance of earthworks in overland flow paths (flooding);
  • Avoidance of earthworks in areas prone to instability and erosion;
  • Avoidance of areas in close proximity to water courses, wetlands, lakes and the coastal marine area;
  • Requirement for re-vegetation, reinstatement and stabilisation of the site;
  • Implementation of erosion and sediment control measures to minimise sediment entering receiving waterbodies in a catchment. Reference is often made to guidelines developed by regional councils.

[ Hide ]

 

District plans

Permitted activities

District plan rules can rely on a range of factors to determine thresholds for permitted activities. These can include:

Any thresholds specified in plans should be based on the effects of the earthworks activities. Technical/engineering advice should be sought in determining the threshold level for permitted activities. Further controls can also be specified where there is potential for significant adverse effects.

Additional District Plan Regulatory Methods

  • Avoidance of earthworks in overland flow paths (flooding);
  • Avoidance of earthworks in areas prone to instability and erosion;
  • Avoidance of areas in close proximity to water courses, wetlands, lakes and the coastal marine area;
  • Thresholds limiting excavations and unretained filling;
  • Avoidance of material deposited on public roads and accessways;
  • Requirement for re-vegetation and stabilisation of the site;
  • Dust control measures to avoid nuisance effects beyond the boundary of the site;
  • Protocols for earthworks where archaeological features are exposed or found; and
  • Implementation of erosion and sediment control measures to minimise sediment entering receiving waterbodies in a catchment. Reference is often made to guidelines developed by city/district councils and / or regional councils

 

[ Hide ]

 

Provisions in district plans for earthworks in sensitive receiving environments

Some plans include standards and terms for earthwork activities.  These apply at the subdivision and development stage when earthworks and the associated sediment discharge can significantly affect the receiving environment. Examples include:

Guidelines

Guidelines are useful tools to assist applicants to comply with district plan requirements. 

Examples of guidelines prepared by city/district councils include:

Other References

Other useful references to consider in the development of district plan provisions for earthworks include:

Conditions on Resource Consents

Use of Management Plans

Management plans (which commonly include “erosion and sediment control plans”) are often required by councils under s.108(3) RMA to manage the effects of earthworks. The purpose of a management plan is to provide information about the way in which the consent holder intends to comply with the more specific controls imposed by consent conditions. (Refer Relevant Case Law).

Some regional councils are now requiring erosion and sediment control plans to be provided as part of a consent application. Not only do these plans assist with assessing the effects of a proposal they can also help to inform the development of appropriate conditions of consent (Refer Generic Example of Sediment Control Plan).

Effects on Archaeological Sites and Sites of Significance to Maori

When assessing the effects of earthworks on cultural heritage features, archaeological sites and sites of significance to Maori it is important to consider what, if any, conditions should be applied.

Areas for consideration include, for example, requiring sites or features not affected by earthworks to be fenced or marked off or requiring an Accidental Discovery Protocol to be prepared in the event that a site is unintentionally uncovered. Refer Historic Heritage Guidance Note , Heritage Management Guidelines for Resource Management Practitioners and Example Archaeological Site Resource Consent Conditions for further details.

Effects of Dust

Dust can create a nuisance by reducing visibility and is an effect on amenity values that can be considered by city and district councils. Refer Example of Dust Management Resource Consent Condition

back to top

RMA Provisions

back to top

Relevant Case Law

A volume of case law is available on individual resource consent applications to undertake earthworks as part of comprehensive site developments. Much less case law is available on policy and plan provisions for earthworks management.

back to top

Related Guidance Notes

back to top

Relevant Publications

Technical Guidelines

Technical Publication No.69: Environmental Impacts of Accelerated Erosion and Sedimentation
Published by Auckland Regional Council - 1996
This publication outlines the physical effects of accelerated erosion and sediment on the environment and includes information from a wide variety of sources.

Technical Publication No.90: Erosion and Sediment Control Guidelines for Land Disturbing Activities in the Auckland Region
Published by Auckland Regional Council - 2008
These guidelines provide a comprehensive overview of the principles of erosion and sediment control and the adverse effects associated with land disturbing activities. Practical management guidance is offered on erosion control, sediment control, works within a watercourse, quarries and vegetation removal.

Technical Publication No.124: Low Impact Design Manual for the Auckland Region
Published 1970
This manual outlines a range of measures for promoting low impact site development, such as buildings, stormwater management, and erosion and sediment control. Case studies are used to highlight the application of low impact site development in different environments.

Soil Conservation Technical Handbook
Published 2001
This handbook provides detailed information on the forms and processes of erosion that occur throughout New Zealand, and outlines techniques for managing these and associated land disturbance activities.

Erosion and Sediment Control: Guidelines for Soil Disturbing Activities – Technical Publication TR2002/01
Published 2003
These are similar in nature to the Auckland Regional Council guidelines (TP90) but with a particular focus on the different soils and environmental characteristics in the Waikato region.

Heritage Guidelines

Heritage Management Guidelines for Resource Management Practitioners
Published by New Zealand Historic Places Trust - August 2004
Guidelines to assist local authorities, owners & developers to identify & manage historic heritage under the RMA, & information on archaeological site obligations under the Historic Places Act.

International Literature

Managing Urban Stormwater: Soil and Construction (4th Edition)
Published April 2004
This document offers a practical guide to erosion and sediment control on urban building sites. A series of fact sheets highlight a range of approaches that can be used, from overall site management to specific management practices.

Soil and Erosion and Sediment Control Guidelines for Queensland Construction Sites
Published 1996
These guidelines provide an overview of the principles of erosion and sediment control management. Different management techniques are discussed, including the particular circumstances where they can be applied.

Urban Erosion and Sediment Control
Published by NSW Department of Conservation and Land Management - 1992
This document describes the effects of land disturbing activities and provides practical advice on a range of management techniques applicable to urban areas. Many NSW local authorities refer to this document in their own guidelines.

back to top

Current Challenges

Integrated Management

Achieving integrated management of earthworks between regional and district plan provisions, as the management issues are closely interrelated. RMA plans need to be clear about the respective responsibilities of each council, including who will assume responsibility for administering the different effects and how will monitoring be carried out and by whom.

Plan Rules - Performance Standards and Thresholds

Resource Consent Conditions

Managing Non-Point Source Discharges

back to top

Acknowledgements

This guidance note was prepared by Catherine Clarke and Hamish Wesney of Boffa Miskell Limited, and Brian Handyside of Erosion Management Ltd. The note was further shaped and reviewed by Greg Vossler and Gina Sweetman of the Ministry for the Environment. The Ministry for the Environment would also like to thank the following people for their input into the preparation of this material:

This guidance note was prepared in March 2007.